DECEMBER IN TORRE MILANO

5th december 2019

The works in Torre Milano started less than a month ago, and several fundamental operations for the construction have already been carried out or are in progress.

In fact, for a length of 13 meters, the concrete CFA poles (reduction of foundation settlements) were thrown into the ground. In these days, the company is scapitozzando the same to continue with the laying of the foundation slab.

The installation of the bases of the two construction site cranes is also underway which will rise over the area within a few days.