THROW OF FOUNDATION OF TORRE MILANO

13rd january 2020

Important day in Torre Milano, where the throw of the foundations took place.

The operations lasted throughout the day, and involved about 45 employees, including technicians, operators, drivers and workers. The entire foundation slab was poured without interruption, using more than 2,000 m3 of total concrete.

In compliance with the construction times, once the foundation casting operations have been completed, we will immediately move on to the construction of the elevation works of the basement floors (pillars and walls) and then continue with the construction of the roof slabs placed on the first basement floor and on the ground floor.